The customer changes a motor, material, control philosophy or delivery date after engineering and supply have started. The obvious cost sits in the revised parts list. The expensive part often sits elsewhere: drawings that must change twice, a supplier order that cannot be cancelled, completed fabrication that needs rework, another factory test, overtime to recover the date and project time spent controlling the change.
Many OEMs find those costs after the customer has accepted the change price. The estimator priced the final design as if the company had known it on day one. That answers the wrong question. The price must cover the difference between finishing the current order and finishing the revised one from its present state.
This guide builds that difference in a form engineering, operations, finance and the customer can audit. It also separates three numbers that teams often mix together: incremental cost, selling price and the amount the contract lets the OEM recover.
Freeze the estimate at one point in time
Set a cutoff date before the team calculates anything. Record the current design revision, supplier commitments, production status, actual cost, open purchase orders, remaining estimate and schedule. The same request can cost $40,000 before release and $240,000 after material arrives. A price without an execution-state date will become false while people review it.
Link the estimate to the exact customer request and order baseline. State what the customer wants, which accepted requirement changes and which units or serial numbers it affects. If the request remains unclear, price the defined interpretation and list the unanswered points as exclusions or risk items.
| Estimate control | Required value |
|---|---|
| Cutoff | Date and time of cost, WIP, supplier and schedule snapshot |
| Order baseline | Accepted scope, configuration, drawings, terms and milestones |
| Change definition | Specific revised requirement and affected units |
| Execution state | Engineering, supply, production, test and site progress |
| Estimate owner | Person responsible for one reconciled price build |
| Validity | Decision deadline and events that require repricing |
Use a before-and-after cost bridge
Calculate the remaining cost of the current order from the cutoff, then calculate the remaining cost of the revised order from the same cutoff. The difference captures future work. Add sunk cost that the change makes useless, cancellation charges, rework and change-specific execution costs. Subtract salvage, supplier refunds and work the OEM no longer needs to perform.
This bridge prevents two common errors. First, it does not charge the customer again for unchanged work already sold. Second, it does not pretend that the company can erase completed work simply because the revised product no longer needs it.
Official change-accounting guidance follows the same logic. FAR 43.203 separates nonrecurring engineering and obsolete or reperformed work, distinct new work, and recurring labor and material. The clause applies to specific government contracts, but its cost categories form a useful check for any complex OEM change.
| Bridge line | Calculation |
|---|---|
| Future cost added | Revised remaining work less unchanged remaining work |
| Future cost removed | Unperformed original work no longer required |
| Stranded cost | Completed or committed work with no value in the revised order |
| Rework cost | Labor, material and services needed to modify usable work |
| Change execution | Analysis, replanning, control, validation and documentation |
| Credits | Refunds, reuse, scrap value and avoided external charges |
| Incremental cost | Added + stranded + rework + execution − removed − credits |
Create a separate cost object for the change
Give the change its own project task, job, work breakdown element or cost code as soon as analysis starts. Charge engineering review, supplier cancellation, rework, extra material, retest and project hours to it. Unchanged work stays on the original order code.
Without a separate object, actual cost disappears into the base job. The estimator cannot compare the estimate with the outcome, finance cannot support the customer price and the next change uses another guess. Time booked before customer approval still belongs in the record, even if the company later chooses not to recover it.
FAR 52.243-6 requires separate accounts for direct costs of certain changed work, less applicable credits. The practical lesson is simple: estimate and collect the change through the same cost structure. A polished proposal has little value if the accounting system cannot show what the change consumed.
| Cost code | Examples |
|---|---|
| Change analysis | Requirements review, design study, supplier inquiry and planning |
| New work | Added design, parts, fabrication, software and documentation |
| Rework | Disassembly, modification, refinish, rebuild and repeat setup |
| Obsolete work | Scrapped design, material, WIP, tooling and supplier output |
| Schedule recovery | Overtime, premium freight, expediting and remobilization |
| Verification | Recalculation, inspection, certification and repeat test |
| Administration | Change control, contract, finance and customer coordination |
Price engineering by deliverable and iteration
Ask each discipline which released and in-progress objects must change. Count calculations, requirements, models, drawings, BOMs, software modules, interface documents, test procedures, manuals and customer submittals. Estimate review and release effort alongside authoring.
Do not price only the final edit. Engineers must inspect the current state, find dependencies, decide what remains valid, update the object, review it and answer downstream questions. A change received during customer drawing approval may also create another customer review cycle.
| Engineering activity | Estimate basis |
|---|---|
| Impact analysis | Hours by discipline to find affected requirements and objects |
| Design change | Hours or standard by calculation, model, drawing, BOM and code unit |
| Independent review | Checker and approver effort by release class |
| Customer submittal | Preparation, review cycle and comment resolution |
| Manufacturing support | Disposition, shop questions, rework instruction and first build |
| Field support | Site survey, procedure, travel, supervision and as-built update |
Use current labor rates and real capacity
Apply the rate that matches the cost method and period of performance. Separate direct pay, labor burden, engineering overhead and selling or general expense according to the company’s normal accounting policy. Do not add the same overhead once in the labor rate and again as a percentage of total cost.
Capacity changes the execution plan. Forty engineering hours during a slack month may use normal time. The same work during a release peak may delay another package or require contract labor. Price the action the team will actually take. If management chooses to absorb an opportunity cost, show it as a commercial decision instead of burying it in a padded hourly rate.
The FAR cost principles draw a firm line between direct and indirect treatment: a company should apply the same treatment to like costs in like circumstances. Private contracts may use different rules, but consistent treatment prevents double counting and makes the estimate easier to defend.
Build the material delta from disposition
For each changed item, record original quantity and cost, revised quantity and cost, current commitment, work completed and final disposition. The disposition matters as much as the price difference. An old component may return to stock, move to another project, incur a restocking fee or become scrap.
Use supplier confirmation for custom and long-lead items. A purchase-order value does not reveal cancellation exposure. Ask what material the supplier bought, which operations it completed, what it can reuse and when the revised part can arrive. Attach the answer to the estimate.
Apply credits explicitly. The current FAR Part 31 deviation guide tells contractors to reduce material cost by discounts, refunds, rebates, scrap, salvage and returned-material credits. Any fair internal method should do the same. Pricing gross added cost while ignoring a real recovery weakens the proposal and distorts margin.
| Original item state | Cost treatment |
|---|---|
| Not ordered | Remove original future cost; add revised item cost |
| Ordered, cancellable | Use cancellation fee and any supplier credit |
| Ordered, amendable | Use supplier price delta, rework and lead-time charge |
| Received, reusable elsewhere | Credit transfer value under company policy |
| Received, returnable | Credit refund less restocking and freight |
| In WIP, modifiable | Add rework, new material and repeat operations |
| Completed, unusable | Add stranded cost less salvage or scrap recovery |
Include rework, scrap and lost learning
Rework includes touch labor, disassembly, movement, cleaning, inspection, new setup, tooling changes, repair material, supervision and repeat quality records. If the work interrupts a production sequence, include the documented loss of efficiency or repeat setup caused by that interruption.
Treat scrap at its net cost. Start with the cost already incurred, add disposal and handling, then subtract salvage or reusable material. Do not price a new replacement and the full original material twice when some value remains.
If the change breaks a planned production run, calculate the effect from the actual routing and state. A broad “10% disruption” line will invite a challenge. Show which crew stops, which operation repeats and which quantity loses the expected learning or batch efficiency.
| Rework element | Evidence |
|---|---|
| Completed operations | Labor and machine transactions through cutoff |
| Undo work | Disassembly, removal, cleaning and access plan |
| Redo work | Revised routing, setup, run and inspection time |
| Material loss | Disposition, recovery value and replacement need |
| Sequence loss | Changed batch, setup or production schedule |
| Quality release | Repair approval, nonconformance and verification plan |
Price supplier changes from written responses
Send every affected supplier the same defined change and cutoff. Ask for added price, credit for removed work, cancellation or amendment charge, tooling effect, new lead time, validity and assumptions. If the supplier cannot quote before the customer deadline, include a named allowance and risk range.
Separate the supplier’s cost from the OEM’s work. The buyer must issue and track the amendment. Engineering may need to review a new drawing. Quality may need another source inspection. Logistics may change. The supplier price covers none of that unless its quote says so.
| Supplier response | Use in estimate |
|---|---|
| Firm revision quote | Use quoted delta, terms and validity |
| Budget quote | Use amount plus explicit confidence or contingency |
| Cancellation quote | Use charge less recoverable material or credit |
| No response | Use documented basis, range and decision deadline |
| Lead-time increase | Carry schedule and recovery effect into project estimate |
| Minimum order change | Price the actual purchase quantity and residual disposition |
Calculate test, certification and documentation again
A design change can invalidate calculations, qualification evidence, inspection results and certificates even when the physical edit looks small. Ask quality and compliance which evidence remains valid. Price new test plans, customer witness time, laboratory fees, certification-body review, sample destruction and updated data books.
Documentation changes can reach manuals, nameplates, spare-parts lists, software records, training and translations. Include the number of affected documents and their approval cycle. A revised operating voltage on the machine without the same revision in the manual creates a field problem the change price should prevent.
Model schedule cost from a recovery plan
A later delivery date can add project supervision, storage, financing, rented equipment, site remobilization and extended supplier support. An earlier date can add overtime, split shipments, premium freight, parallel work and expedited supplier charges. Price the dated plan, not a generic acceleration percentage.
Build at least two cases when the customer has a choice. One case shows the natural date at normal execution cost. Another shows the requested date and each recovery action. The price difference gives the customer a real schedule decision.
| Schedule action | Cost to include |
|---|---|
| Overtime | Premium pay, efficiency, supervision and support coverage |
| Parallel engineering | Extra coordination, review and configuration-control load |
| Premium freight | Supplier-to-plant and plant-to-site transport by route |
| Split delivery | Packing, handling, documents and site receiving for each lot |
| Delay | Extended project, storage, rentals, guarantees and escalation |
| Remobilization | Travel, site access, labor minimums and equipment return |
Separate disruption from the changed work
Changed work has a direct scope. Disruption is the effect on otherwise unchanged work: crews wait, sequences break, engineers switch context, a line stops or a test slot disappears. Estimate disruption only when the team can explain the cause, affected work, duration and calculation.
Use records available at the cutoff: schedule logic, time bookings, production transactions, hold notices, queue changes and resource plans. Compare the planned and revised method. If the company has no evidence, present the exposure as a risk range instead of a false exact amount.
| Claimed effect | Support needed |
|---|---|
| Idle labor | Named crew, hours, reason it could not move to other work |
| Lost production slot | Original schedule, replacement slot and affected output |
| Repeated setup | Original and revised routing or setup records |
| Engineering interruption | Affected package, stop/start work and additional review |
| Site inefficiency | Daily records, access restriction and revised method |
Apply overhead once and consistently
Use the company’s normal costing structure. Direct engineering may carry engineering burden. Shop labor may carry factory overhead. Material may carry purchasing or handling burden. General and administrative expense may apply to an accepted base. Write the rate, base and period beside each calculation.
Check every rate for double counting. A fully burdened shop rate should not receive the same factory overhead again. A supplier quote may already include freight. An expedite fee may already include overtime. Reconcile the estimate from raw cost to total cost so finance can see every layer.
Do not remove overhead from deleted work while leaving the same fixed expense spread over less production without thought. Credits should follow the contract and pricing method, while internal margin analysis should show the real cost behavior. The customer price and the internal economic effect can differ.
| Rate check | Question |
|---|---|
| Direct labor | Does the hourly rate contain payroll burden or department overhead? |
| Material burden | Which purchasing, receiving, handling or inventory costs apply? |
| Factory overhead | Which machine, supervision, facility and support costs sit in the pool? |
| Engineering overhead | Which management, tools and support costs sit above direct hours? |
| G&A | Which base receives it, and does the customer agreement restrict it? |
| Escalation | Which rate period matches when the revised work will occur? |
Credit deleted work on the same logic
A deletion credit is not automatically the original selling price of the removed item. The OEM may have completed design, ordered material or incurred setup before deletion. Calculate which future costs the company truly avoids, which committed costs remain and which recoveries it receives. Then apply the agreed pricing rule.
Use the same structure for adds and deletes. If added subcontract work receives material handling, overhead and margin, decide how the contract treats those elements on deleted subcontract work. Inconsistent treatment creates a one-way price formula that customers will challenge.
A longstanding GAO review of credit change orders identified exactly this asymmetry: overhead and profit appeared on added work while deletions received no corresponding adjustment. The report concerned GSA construction contracts, but the warning applies to OEM pricing. Show additions and credits through one visible bridge.
| Deleted-scope state | Credit basis |
|---|---|
| No work or commitment | Avoided future cost under the agreed pricing rule |
| Engineering partly complete | Avoided remaining work; retain incurred work |
| Material cancellable | Avoided cost less cancellation and handling |
| Material reusable | Credit recoverable value under policy |
| WIP reworked into new scope | Credit avoided completion; add modification cost |
| Completed item scrapped | No avoided production cost; credit recovery value |
Add contingency by named risk
List uncertain quantities, supplier responses, engineering hours, test outcomes and schedule assumptions. Give each risk a range and basis. Use expected value or another approved method. A flat contingency percentage hides which uncertainty the customer can remove with a quick decision.
Do not use contingency to cover missing scope the team could define. Ask the question, get the supplier quote or complete the impact review. Retain contingency for uncertainty that remains after reasonable analysis. State whether unused contingency stays in the fixed change price or reconciles later.
| Risk | Low | Most likely | High | Retirement event |
|---|---|---|---|---|
| Transformer cancellation | $18k | $31k | $44k | Supplier confirms disposition |
| Panel rework | 120 h | 180 h | 290 h | Shop completes first panel inspection |
| Repeat test | 1 day | 2 days | 4 days | Customer approves revised FAT plan |
| Premium freight | $9k | $14k | $23k | Supplier confirms ship date |
Set price from the revised commercial exposure
Once the team has incremental cost, set the selling price. Apply the margin target for the product, customer and risk. A change that consumes scarce engineering capacity, weakens performance confidence or creates a compressed date may deserve a higher return than the original order. A strategic concession should appear as a visible discount with named approval.
Check the contract before presenting the price. It may define labor rates, markups, notice periods, audit rights, fee limits or time-and-material treatment. Those terms govern the recoverable amount. The internal cost estimate still needs the full economic effect so management can see any gap it chooses or must absorb.
| Number | Meaning |
|---|---|
| Incremental cost | Expected economic cost of finishing the revised order |
| Target price | Cost plus approved margin and risk treatment |
| Contract-supported amount | Amount recoverable under the agreed change terms |
| Proposed price | Amount sent to the customer after commercial strategy |
| Agreed price | Final authorized customer adjustment |
| Absorbed exposure | Cost the OEM expects to carry after agreement |
Reconcile the customer price to the estimate
The proposal total should reconcile to a controlled estimate version. Every line should have a basis: quantity, hours, rate, supplier response, routing, historical case or explicit allowance. Keep internal margin and sensitive supplier detail in the approval view while giving the customer enough structure to understand the price.
If negotiation changes the price, record the concession against the same estimate. Do not edit cost down to make the agreed margin look better. The final record should show target price, concession, agreed price and remaining exposure.
| Proposal layer | Customer view | Internal view |
|---|---|---|
| Scope | Revised supply, exclusions and assumptions | Affected baseline objects and owners |
| Engineering | Defined design and documentation work | Hours, rates and deliverables by discipline |
| Supply and production | Material, fabrication and modification | Supplier quotes, WIP and disposition |
| Schedule | Natural date and priced recovery option | Critical path, resource and expedite detail |
| Commercial | Price, payment, validity and authorization | Margin, risk, concession and recovery gap |
Worked example: change a conveyor drive after fabrication starts
An OEM has a $4.8 million order for a bulk-material conveyor system. The customer asks for regenerative drives and a higher hazardous-area classification after electrical drawings have been approved. Panel fabrication is 35% complete. The drive supplier has started the original units. The customer still wants the accepted shipment date.
The team sets Tuesday at 4 p.m. as the cutoff. It creates one change cost code and freezes the current configuration, WIP and commitments. Engineering identifies 312 hours across controls, electrical, mechanical interfaces, software, checking and manuals. At current rates and burdens, engineering adds $48,600.
The new drives cost $74,000 more. The supplier charges $21,500 for work already completed on the old units and credits $8,000 for reusable components. Panel rework adds $32,700. Repeat certification and FAT add $18,400. Project control, procurement and quality add $11,800. Premium freight, overtime and a second test shift add $39,000 to hold the date. The OEM removes $6,500 of unperformed original work.
Incremental cost equals $232,500. Three named risks add $17,500 of expected cost, bringing the priced cost to $250,000. At the approved margin, the target customer price is $322,600. Commercial management approves a $12,600 concession for the account, so the proposal is $310,000 with a seven-day validity and a customer decision deadline tied to the supplier slot.
The customer asks why the drive price delta is only $74,000 while the change costs $310,000. The proposal shows the answer without exposing internal margin: engineering release, supplier settlement, panel rework, certification, schedule recovery and changed documentation. The customer accepts the price. Actual cost closes at $244,800, 2.1% below the priced cost.
| Cost element | Amount |
|---|---|
| Engineering | $48,600 |
| Drive price delta | $74,000 |
| Supplier stranded cost less credit | $13,500 |
| Panel rework | $32,700 |
| Certification and repeat FAT | $18,400 |
| Project, procurement and quality | $11,800 |
| Schedule recovery | $39,000 |
| Removed future work credit | −$6,500 |
| Expected risk | $17,500 |
| Priced cost | $250,000 |
| Target price | $322,600 |
| Proposed and agreed price | $310,000 |
Review actual cost when the change closes
Compare estimated and actual hours, material, supplier charges, rework, schedule recovery and credits. Explain the variance by cause. Do not stop at total favorable or unfavorable cost. A favorable supplier outcome can hide an engineering overrun that will repeat on the next change.
Feed the result into standards and future bids. If panel rework repeatedly takes twice the estimate, update the routing or model. If customer decisions routinely expire supplier validity, shorten the proposal window or price the exposure. If many changes originate in unclear product options, repair configuration and proposal rules upstream.
SAP’s preliminary manufacturing order costing compares planned cost with later production variance and recalculates planned cost when an order changes, depending on setup. That same planned-versus-actual discipline should exist for each material engineering change.
| Variance | Question to answer |
|---|---|
| Engineering hours | Did the team miss affected objects, iteration or review effort? |
| Material | Did quantity, price, scrap or recovery differ? |
| Supplier | Did the final settlement match the quoted amendment? |
| Rework | Did the routing reflect the actual factory method? |
| Schedule | Did the team execute the priced recovery plan? |
| Credits | Did refunds, reuse and salvage reach the job? |
| Margin | Which concession or cost variance changed the return? |
How Bourne builds the change price
Bourne starts from the accepted order, current configuration and execution state. It collects engineering impact, supplier responses, purchase commitments, WIP, actual cost, remaining work, schedule options and contract rules. The result is one before-and-after price bridge with a source behind every material number.
The application can draft requests to suppliers and internal owners, assemble the change estimate, identify missing credits and flag rates or cost categories that appear twice. Estimators and commercial leaders approve the cost basis, risk, margin and customer presentation.
After agreement, Bourne writes the approved value and scope to CRM, ERP and project records, then tracks actual cost against the estimate. The next engineering change starts with measured rework, supplier and schedule history from comparable work.
Use a live change to test the method
Pick a current change with released engineering, at least one supplier commitment and a schedule question. Rebuild the estimate with the bridge in this guide. Require written dispositions for affected material and WIP. Ask every discipline to name its deliverables and hours. Build a normal-date and recovery-date option.
The test passes when the cost reconciles, deleted work receives a supportable credit, no overhead appears twice, each risk has a basis and the proposed price ties to the approved estimate. Continue charging actual work to the same cost object until closure.
Then compare the result with the company’s original shortcut. The difference is usually where margin has been leaking: stranded commitments, engineering iteration, repeat verification, schedule recovery and work performed before the customer signs.
| Test | Pass condition |
|---|---|
| Cutoff | Cost, WIP, commitments and schedule share one dated snapshot |
| Bridge | Added, removed, stranded, reworked and credited cost reconcile |
| Rates | Each burden and overhead appears once on the correct base |
| Evidence | Material amounts trace to a record, quote, routing or assumption |
| Commercial | Margin, risk, concession and contract recovery remain distinct |
| Actuals | The accounting object collects the cost categories in the estimate |
Bourne for manufacturing
See what Bourne could do for your quoting team.
Bring a customer request and the steps your team takes to quote it. We’ll discuss the application, integrations and approvals you need.